Table 5b: Earthworks in specific locations |
Activity status
|
All locations
|
The diversion or modification of streams and waterways within the Stream Protection A Area, except for the realignment of stream 1B and works associated with steam bank rehabilitation and revegetation
|
NC |
Works associated with stream bank rehabilitation and revegetation of waterways within the Stream Protection A Area, and the realignment of stream 1B within the Stream Protection A and B Areas.
|
D |
The diversion or modification of streams and waterways in Stream Protection B Area, except for the main channel of the Vaughan and Awaruku Streams and stream 2 within Long Bay sub-precinct G.
|
P |
The disturbance of an area of 100m2 or volume of 10m3 or greater, either wholly or partially within any secondary flow path or 1% AEP flood plain
|
D |
Modification of the areal extent of the 1% AEP flood plain either within the site, or on upstream or downstream sites
|
D |
Works that relocate or disturb an existing secondary flow path in the Stream Protection A Area, or a post development secondary flow path in the Stream Protection B Area
|
D |
Earthworks located less than 5m from any cliff face
|
D |
Earthworks situated on land with a gradient of 1:4 or steeper
|
D |
Earthworks within 30m of a scheduled archaeological site and within the part of the 30m buffer of site 1082 that is in the riparian margin of the Vaughan Stream
|
D |
Long Bay Sub-Precinct C Area 2
|
Retaining walls on the western boundary of Long Bay sub-precinct G which have the effect of raising the ground level less than 1m high
|
D |
Long Bay Sub-Precinct G
|
Earthworks in accordance with an approved Heritage Management Plan
|
D |
Earthworks not in accordance with an approved Heritage Management Plan
|
Pr |
Protection Areas
|
1. Piripiri Point Protection Area
|
Earthworks ancillary to a permitted activity (as set out in Table 3 above)
|
P |
Earthworks to create a ridgeline in accordance with the Ridgeline Height Control and Spot Heights as shown on Precinct Plan 5 and associated earthwork contours in an approved framework plan
|
RD |
Earthworks to create the ridgeline not in accordance with the Ridgeline Height Control and Spot Heights shown on Precinct Plan 5, provided it is in accordance with an approved framework plan
|
D |
Earthworks for public roading
|
D |
All other earthworks
|
NC |
2. Park Interface Protection Area
|
Earthworks to create the ridgeline in accordance with Ridgeline Height Control and Spots Heights, as shown on Precinct Plan 5 and associated earthwork contours in an approved framework plan
|
RD |
Earthworks to create the ridgeline not in accordance with the Ridgeline Height Control and Spot Heights shown on Precinct Plan 5, provided it is in accordance with an approved framework plan
|
D |
Earthworks to the north and east of the Ridgeline Height Control Line once the ridge is formed and site works which lower the height of the constructed ridgeline, except for site works for revegetation and fencing purposes which are permitted
|
Pr |
Earthworks to the west and south of the Ridgeline Height Control Line once the ridge is formed have the following status:
•Earthworks which expose up to 25m2 of bare earth
•Earthworks which expose 25m2 or more of bare earth
•Retaining walls which have the effect of raising the ground level by up to 1.5m above natural ground level (measured by the vertical distance from the top to the bottom of the wall).
•Retaining walls which have the effect of raising the ground level by more than 1.5m above natural ground level (measured by the vertical distance from the top to the bottom of the wall)
|
P
|
D |
P |
D |
All other earthworks
|
NC |
3. Vegetation– Conservation Area
|
Earthworks for the purposes of installing surface laid wastewater disposal fields and tracks for public recreation
|
D |
All other earthworks
|
NC |
4. Long Bay - Vegetation– restoration
|
Earthworks directly associated with revegetation, fencing and walking tracks
|
P |
All other earthworks
|
NC |
5. Riparian Margins
|
Earthworks for tracks that provide for public access to and along a public reserve more than 5m from the top of the bank of a stream, and site works directly associated with revegetation
|
P |